Sakhalinskaya SDPP-2, 1st stage

 

 

Location

Sakhalin Island,

ME Tomarinsk Urban District 

Project mission

Coverage of electrical power shortfall on Sakhalin Island; replacement of the retired capacity of the existing Sakhalin SDPP

Installed capacity, MW

120 MW

Number of hydroelectric units, pcs * MW

2*60

Average annual power generation, million kW*h

840

Year and volume of commissioned capacity

2019

120 MW

Year of project completion

2019

Technical readiness as of 01.01.2019

89%

 

Sovetskaya Gavan CHP

 

 

Location

Sovetskaya Gavan, Khabarovsk Territory

Project mission

Coverage of the electric power requirements of the Vanino-Sovetsko-Gavansky hub, provision of Sovetskaya Gavan with a centralized heat supply

Installed capacity, MW

126 MW/200 Gcal/hr

Average annual power generation, million kW*h

630

Year and volume of commissioned capacity

2019

126 MW/200 Gcal/hr

Year of project completion

2020

Technical readiness as of 01.01.2019

54%

 

Nizhny-Bureyskaya HPP

 

 

Location

Amur Region

Bureysky District

Novobureysky

Project mission

Counter-regulator for the Bureyskaya HPP, generation of electricity

Installed capacity, MW

320

Number of hydroelectric units, pcs * MW

4*80

Average annual power generation, million kW*h

1,670

Year and volume of commissioned capacity

2019 - commisioning of 320 MW

Year of project completion

2019

Technical readiness as of 01.01.2019

84%

 

Ust-Srednekanskaya HPP

 

 


Location

Magadan Region, Srednekansky District

Project mission

Improvement of the reliability of the energy system, electricity supply for mining companies in the region

Installed capacity, MW

570

Number of hydroelectric units, pcs * MW

4 HU * 142.5

Average annual power generation, million kW*h

2,555

Year and volume of commissioned capacity

2013 - commissioning of HU No. 1, No. 2 at a reduced pressure

2018 - commissioning of HU No. 3

2022 - commissioning of HU No. 4

Year of project completion

2023

Technical readiness as of 01.01.2019

62%

  

Zaramagskie HPP

 

 


Location

RNO - Alanya, Alagirsky District,  Mizur

Project mission

Electricity production, coverage of power shortfall at RNO-Alania from 80% to 30%

Installed capacity, MW

356

Number of hydroelectric units, pcs * MW

10 + 2 * 173 MW

Average annual power generation, million kW*h

842

Year and volume of commissioned capacity

Principal HPP - 15 MW commissioned in 2009;

HPP-1 - 346 MW - 2019

Year of project completion

2019

Technical readiness as of 01.01.2019

96%