JSC RusHydro sets up a Directorate for elimination of the consequences of the accident

On 19 August, 2009, by resolution of the Acting Chairman of the Management Board of JSC RusHydro Vasily Zubakin, a Directorate was set up for elimination of the consequences of the accident.  Chief Engineer of the Sayano-Shushenskaya HPP Andrey Mitrofanov has been appointed to take on the additional job of Head of the Directorate.

To combat the consequences of the accident, the holding company’s best power-repair, engineering and construction personnel are being mobilised.  More than 400 specialists are being sent to the power station:

  • ChirkeyGESstroy — 200 persons (general building specialties)
  • Energostroy LTD. — 50 persons (turbine, generator and transformer-repair experts)
  • Gidroremont — 50 persons (installation and concreting specialists)
  • Turboremont — 40 persons (installation and turbine specialists)
  • Elektroremont — 57 persons (generator experts, wiremen, specialists in repairing switchgear and transformers)

 