22.09.2009
printable version
RSS

Work has been initiated under a programme of pre-commissioning testing of the third hydro-units at the Bureiskaya HPP

On 21 September, a cycle of pre-commissioning testing of the third hydro-unit at the Bureiskaya HPP was launched according to schedule.   

Repairs were launched to the third hydro-unit of the Bureiskaya HPP in connection with the planned rise in the penstock from the 216 to the 243-metre mark.  During the planned halt, the hydro-unit was inspected and repair works were carried out.  The tests carried out at this time were necessary for ensuring the continued reliable and safe work of the third hydro-unit.  

The plan is to start-up the third hydro-unit at the Bureiskaya HPP under load in November this year, its capacity amounting to 335 MW. 