RusHydro dams Bureya river to complete the construction of Nizhne-Bureyskaya hydropower plant in the Far East

PJSC RusHydro (ticker symbol: MOEX, LSE: HYDR; OTCQX: RSHYY) announces that the Bureya river in the Amur region has been dammed up and the river now flows through the Nizhne-Bureyskaya hydropower plant.

The river damming allows to complete the construction of the main retaining structures of the plant. The length of the ground dam is 400 m, full height – 41.5 m.

The concrete structures of the Nizhne-Bureyskaya HPP are 90% ready. Two hydropower units manufactured by Power Machines are being installed in the turbine room.

The Nizhne-Bureyskaya HPP, counter-regulator for the Bureyskaya HPP, is the second plant of the Bureya Hydropower Complex in the Amur Region. The project capacity of the Nizhne-Bureyskaya HPP is 320 MW (four hydro units); average annual output will be 1,650 GW. The plant’s construction has started in 2010; it is one of priority projects of RusHydro’s investment program.
The information in this press release may contain projections or other forward-looking statements regarding future events or the future financial performance of RusHydro. You can identify forward looking statements by terms such as "expect," "believe," "anticipate," "estimate," "intend," "will," "could," "may" or "might," the negative of such terms or other similar expressions. We wish to caution you that these statements are only predictions and that actual events or results may differ materially from these statements. We do not intend to update these statements to reflect events and circumstances occurring after the date hereof or to reflect the occurrence of unanticipated events. Many factors could cause the actual results to differ materially from those contained in our projections or forward-looking statements, including, among others, general economic conditions, our competitive environment, risks associated with operating in Russia, rapid technological and market change in our industries, as well as many other risks specifically related to RusHydro and its operations.