RusHydro launches new 640 MW hydro-unit at the Sayano-Shushenskaya hydropower plant

JSC RusHydro (ticker symbol: MOEX, LSE: HYDR; OTCQX: RSHYY) announces that a new 640 MW hydropower unit was commissioned and put into commercial operation at the Company's Sayano-Shushenskaya hydropower plant.


In 2013, three hydropower units were commissioned at the Sayano-Shushenskaya HPP with total installed capacity of 1,920 MW. The plant has produced 23 GWh in 2013.


The new unit is the seventh one that was put into commercial operation as part of rehabilitation and comprehensive modernization of the Sayano-Shushenskaya station. Currently, the working capacity of the 6,400 MW plant is 4,480 MW with seven units in operation. The restoration of the units No. 3 and 4 continues and is planned to be completed in March and June 2014 respectively.


The reconstruction of the Sayano-Shushenskaya hydropower plant has now reached the final stage. The plant will be fully equipped with new up-to-date equipment with enhanced performance characteristics that meet all safety and reliability requirements by 2014. The useful life of the new units has been extended to 40 years and maximum efficiency now reaches 96.6%. They also have improved energy and cavitation features. The turbines will be fitted with a more efficient process protection system, which will automatically shut down the unit in case of any inadmissible deviations from controlled parameters.

The information in this press release may contain projections or other forward-looking statements regarding future events or the future financial performance of RusHydro. You can identify forward looking statements by terms such as "expect," "believe," "anticipate," "estimate," "intend," "will," "could," "may" or "might," the negative of such terms or other similar expressions. We wish to caution you that these statements are only predictions and that actual events or results may differ materially from these statements. We do not intend to update these statements to reflect events and circumstances occurring after the date hereof or to reflect the occurrence of unanticipated events. Many factors could cause the actual results to differ materially from those contained in our projections or forward-looking statements, including, among others, general economic conditions, our competitive environment, risks associated with operating in Russia, rapid technological and market change in our industries, as well as many other risks specifically related to RusHydro and its operations.