2004
  • Companie created under Russian Government Decree № 1254-r (dated 01.09.2003)
2005-
2008 
  • Hydro-power generation assets of the re-organized OJSC RAO UES of Russia holding united
2007
  • The Russian Federation becomes one of the Company’s shareholders via an additional share issue
2008
  • The Company’s shares are listed on the Russian stock market
  • A depositary receipt (DR) program is launched
2009
  • Depositary receipts (DRs) listed on the London Stock Exchange (LSE)
2010
  • Completion of the first stage of restoration at the Sayano-Shushenskaya HPP
  • Completion of the Kashkhatau HPP and the Egorlykskaya HPP-2 construction
  • Consolidation of existing hydro-power assets in Siberia
2011
  • Acquisitions of assets in Russia’s Far East
2012
  • Implementation of electricity supply from the first hydro-power units of the Boguchanskaya HPP
  • Update of approximately 500 MW of generating capacity
  • Recapitalization of the Company in compliance with the Russian President’s Decree No.1564
2013
  • The construction of the first stage of Ust-Srednekanskaya HPP in the Magadan Region was completed
  • Modernization of 10 hydropower units of HPPs with overall capacity of 705 MW
  • The Company chaired the Global Sustaiable Electricity Partnership during the period from June 2013 to May 2014
2014
  • The recently completed year draw a line under a major hydropower sector project – construction of the Boguchanskaya HPP with a total capacity of 2,997 MW
  • The Company has completed major restoration and reconstruction work at the Sayano-Shushenskaya HPP
  • RusHydro organized the summit of the Global Sustainable Electricity Partnership (GSEP) in Moscow, which unites 14 of the world’s largest energy companies
  • One of the key outcomes of the Summit was the decision about the prospects for developing and the creating a new generation of energy systems
  • The Company signed an agreement with Three Groges, the Chinese company. The agreement is aimed at joining implementation of Russian Far East hydropower projects
  • RusHydro entered into an agreement with a Chinese concern, PowerChina, on the joint construction of pumped storage plants
2015
  • The Russian Institute of Directors increased the corporate governance rating of RusHydro to level 8.
  • The Boguchanskaya HPP’s reservoir was filled to its project level, the HPP reached its project level of electrical energy output.
  • The Annual General Meeting of Shareholders approved dividends - 6,03 billion roubles.
  • The Gotsatlinskaya HPP was commissioned.
  • The first phase of the second stage of the Blagoveshenskaya CHPP was completed.
  • RusHydro modernised the generating equipment with a capacity of 1,212 MW
  • RAO ES of the East constructed the largest solar power plant in the Arctic Circle.
2016
  • Zaragizhskaya Small HPP in Kabardino-Balkaria was commissioned
  • Zelenchukskaya HPP-PSHPP in the Karachay-Cherkess Republic was inaugurated
  • The second stage of the Blagoveshenskaya CHPP was completed
  • Two solar power plants in Yakutia were commissioned
  • The Annual General Meeting of Shareholders approved the highest dividends for the entire history – 15 billion roubles